Kevin Brown
Member
- Messages
- 111
- Location
- Monroeville, IN(Fort Wayne)
We are finishing our basement and putting in an engineered hardwood floor, that is tongue & grooved, glued together, but floats on top of concrete slab.
The cabinet guy tells me to put the floor in AFTER he builds the 2X4 wall and installs the bar, but the framer that helped me get ready for drywall says to put the floor down BEFORE the cabinets.
Who's right, or what is the recommended way
The cabinet guy tells me to put the floor in AFTER he builds the 2X4 wall and installs the bar, but the framer that helped me get ready for drywall says to put the floor down BEFORE the cabinets.
Who's right, or what is the recommended way